|
|
Construction Method |
|
Preparatory
works
Construction of the installation sites in Wannenboden, Reppisch Valley
and Gänziloo were begun in June 1999 (treatment facilities for the
tunnel, excavation and surface water, drainage systems with stormwater
and wastewater pipes, surfaced site road systems etc.).
The tunnel will be driven downwards from the Reppisch
Valley excavation site under the Uetliberg through to the Zurich-South
interchange in the Brunau area (SG-DIE, MO-UET).
The upward driving of the Juchegg soft ground section (SG-JUC) will be
driven from the Gänziloo excavation site (Brunau side).
The downward driving of the Gjuch soft ground section (SG-GJU), followed
by the 500 m long Eichholz molasse section (MO-EIC), will be driven from
the Wannenboden excavation site under the Ettenberg in the direction of
the excavation site in the Reppisch Valley.
|
|
The
Gjuch, Diebis and Juchegg soft ground sections All
the soft ground sections are being driven using the core construction method.
The excavation support in the soft ground sections consist of steel arches
(HEM 180 girders spaced 1 m apart) and 25 cm thick steel fiber reinforced
shotcrete.
Some large-scale support measures will be necessary to cut through these
ground conditions which, in geotechnical terms, are extremely difficult
(injection, water table lowering, preliminary drainage bores etc.).
|
|

Dividing of soft ground cross-sections
|
|
|
|
|
The molasse sections The Eichholz molasse
section will be excavated in the extension of the Gjuch soft ground section.
The crown of the tunnel will be driven by drill and blast, core, left and
right side walls and base are excavated by ripping. The standard rock support
is generally mesh-reinforced shotcrete and rock bolts.
In critical areas, particularly in the section driven under the SBB-Landikon
tunnel, steel supports have been specified.
In the Uetliberg molasse section, the tunnel
is being excavated using a tunnel boring machine (5.0 m diameter) followed
by a tunnel bore extender (TBE) which applies undercutting techniques.

The tunnel bore extender will be used to widen the previously cut pilot
tunnel to its full cross-section diameter of 14.20 to 14.40 m. The safety
equipment, comprising of cable bolts, Swellex rock bolts, mesh and shotcrete
(possibility exists to install steel) will be installed directly behind
the boring head. |
|
|
|
 |
|
The
sealing, the base, the service duct (prefabricated elements) and back fill
on the sides will be installed from the back-up equipment. |
|
|
|
 |
|
The
lining and the intermediate ceiling will be installed in stages in the rear. |
|
 |
 |
 |
 |
 |
 |
 |